By late September, Skyridge Park already had its new concrete and asphalt, along with the trees, irrigation and benches. All of that work was done. So why were the fences still up as November arrived?
The play structures for all four of Pacifica's Priority Parks come in on a separate contract, and one company installs them one park at a time. That decision saved the project money. It also set the order in which Imperial, Skyridge, Brighton and Marvilla parks reopen.
The slides and swings were bought separately to save money
The project almost didn't happen at this scale. When the City of Pacifica went out to bid in November 2024, offers came back between $2.8 million and $3.2 million. The city's own estimate for the work was about $1.6 million.
The redesign presented in July 2025 cut costs in several places. The change that shaped everything after it was having the city buy the playground equipment directly instead of having the general contractor supply it.
That gave the project two separate contracts. Coastside News reported that the City Council awarded an $888,000 construction contract to Redwood Engineering Construction, the lowest bidder. The council also approved nearly $835,000 for KOMPAN, the playground equipment company. Redwood does the grading, concrete, planting and furnishings. KOMPAN installs the structures kids actually climb on. A park can't reopen until both are done.
One installer, four parks, a set order
The September 23, 2026 update to the Parks, Beaches and Recreation Commission spelled out the sequence. Here is how each park stood then:
- Imperial Park: Tree planting, irrigation and site furnishings were done, and most site work was finished. The last asphalt work was held until after the play equipment goes in. Public Works was waiting for the KOMPAN agreement to be fully executed before giving the green light for installation. The estimated reopening was mid-November.
- Skyridge Park: All site work was complete. KOMPAN was expected to start here after finishing at Imperial. The estimated reopening was early November.
- Brighton Park: Demolition was done and rough grading was finished. The concrete curb for the play area was being formed, and the pour was tentatively set for the week of September 20. Flatwork, planting, irrigation and furnishings would come after that. The estimated reopening was mid-November.
- Marvilla Park: Work was set to follow Brighton, with demolition tentatively in early October. It was expected to reopen last, in late November.
Skyridge is the clearest example. Its site was finished first, but it was second in line for equipment, so it waited on paperwork and installation at a park across town. An August staff announcement put it the same way: Skyridge's equipment would go in after Imperial's, and Skyridge was still expected to be the first park to reopen.
How the dates have moved
Each update pushed the timeline back, and each one pointed to the equipment.
| Park | Location | March 2026 grand-opening target | September 2026 reopening estimate |
|---|---|---|---|
| Imperial | Fairmont District | Late August 2026 | Mid-November |
| Skyridge | Skyridge Drive | Late August 2026 | Early November |
| Brighton Mini Park | Sharp Park District | Late Sept/early Oct 2026 | Mid-November |
| Marvilla | Linda Mar District | Late Sept/early Oct 2026 | Late November |
The March 25 commission presentation already marked Brighton and Marvilla as "delayed due to equipment delivery." Brighton was planned to close in late June, and the city's project page now lists its start as August 20. Marvilla was planned to close in late July, and its listed start is October 26.
The October 28 commission packet gave a range of early to late November for all four parks. Director Scott Leslie noted that dates could still shift with weather and other factors, and commissioners asked specifically about equipment and weather delays. The same packet sets a goal of finishing all four projects by the end of 2026. Meanwhile, the city's Priority Parks Project page lists all four parks as in progress, with overall completion estimated for January 2027.
Read the dates with the queue in mind. A November estimate for a park assumes the parks ahead of it finished on time. The January 2027 date leaves room for the queue to slip. The city has said it will share reopening dates and any celebrations once they are confirmed.
What's coming back, and what was trimmed
The new parks are a simpler version of what neighbors saw in the original designs. The early concept called for replacement wooden play structures, accessible play surfacing, new picnic tables and benches, wider and better paths, and accessible entrances. According to Coastside News, renderings shown to the council featured wooden and metal play structures on mixed surfaces such as woodchips and turf. The outlet also reported that a "Play Tower With Slide & Desk" and a new swing set are among the pieces replacing the rusted old equipment.
The July 2025 cost cuts changed what you'll see on the ground:
- Across the project: Rubber play surfacing became Fibar with concrete ramps. Most planted groundcover and irrigation were removed, and wood mulch replaced the low shrubs. Dog-waste stations and signs came out of the bid, and the city may install them later.
- Brighton: Colored concrete, two benches, concrete piers and a wooden bridge were cut, and the wall features were reduced. A French drain became ¾-inch drain rock, and one tree was added.
- Skyridge: There is less concrete surfacing throughout, and one concrete bench was removed.
- Imperial: The concrete log features in the play area and one bench were cut.
- Marvilla: The full redesign was dropped. Marvilla keeps its current footprint and gets pathway improvements, new seating and replacement play structures. The city describes it as already in the best condition of the four.
Marvilla's smaller scope explains why it comes last. In the July 2025 plan it was an add-alternate, built only if the budget allowed. It also carried no irrigation, groundcover or layout changes. On the bid schedule, Redwood bid $120,000 for the Marvilla add-alternate, and its base bids were $207,058 for Brighton, $263,699 for Imperial and $297,243 for Skyridge.
A 2006 gift is paying for almost all of it
Pacifica's general fund is not paying for these playgrounds. Coastside News reported that the project is funded almost entirely by the Roy Davies Fund. The fund started as a $3.9 million gift from a longtime resident in 2006, and about $2 million of it remains. The fund still earns the city more than $100,000 in interest each year. The Park and Playfield In-Lieu Fund is covering the additional cost of nearly $110,000.
If you have spent time at Fairmont Park, you've seen this money at work before. Coastside News has reported that after the gift arrived, the city used part of it for a new roof on the Community Center and a playground at Fairmont Park. The fund has also paid for other building repairs, playground upgrades and summer-program scholarships.
That's also why these four parks were chosen. The parks came out of a community prioritization process that began in 2022, with surveys, site assessments and input from the commission. The goal was to improve smaller neighborhood parks that had received fewer capital improvements over the years. At the council meeting, Councilmember Sue Beckmeyer summed up the mood in Coastside News' account: "All of these are going to be such improvements. What a thrill."
If you live next to one of the sites
Construction runs Monday through Friday, 8 a.m. to 5 p.m., and the city warns that some of the work can be noisy. Building in phases is meant to keep each park's closure as short as possible. For questions about a specific site, call Public Works Engineering at (650) 738-3767. Brighton Mini Park is at 497 Brighton Road, and the other three are on Imperial Drive, Skyridge Drive and Marvilla Place. The city's project page is the place to check for reopening dates. If you'd like to follow other Pacifica public works projects, the Pacifica Pier timeline is another example of funding shaping a project's schedule.
If you live near Imperial, Skyridge, Brighton or Marvilla and want to talk through what's changing around you in Pacifica, I'd love to hear from you. And if you're curious what your own home is worth this season, request a free home valuation from Real Estate by Shanti.